CUET (UG) 2026 GAT · 14 May (Shift 1) · QA · Question 8
CUET (UG) 2026 GAT · 14 May (Shift 1) previous year question on Time and Work, with the answer and a step-by-step solution.
A can complete a piece of work in 12 days and B can complete the same work in 18 days. Working together, they will finish it in
- A7.2 days
- B7.5 days
- C6.8 days
- D8 days
Pick an option, then check.
Answer & solution
Answer: Option A
In one day A does \frac{1}{12} of the work and B does \frac{1}{18}. Together their one-day work is \frac{1}{12}+\frac{1}{18}=\frac{3}{36}+\frac{2}{36}=\frac{5}{36}. The time taken is the reciprocal, \frac{36}{5}=7.2 days.
More Time and Work questions
- Q5A is twice as good a workman as B, and together they finish a piece of work in 12 days. A alone would finish it inCUET (UG) 2025 GAT · 3 Jun (Shift 2) · QA · Time and Work
- Q5Twelve men can complete a piece of work in 18 days. How many days will nine men take to complete the same work?CUET (UG) 2026 GAT · 18 May (Shift 1) · QA · Time and Work
- Q6A and B together can complete a piece of work in 12 days. A alone can complete it in 20 days. B alone will takeCUET (UG) 2025 GAT · 19 May (Shift 1) · QA · Time and Work
- Q5One pipe fills a tank in 6 hours and another empties it in 9 hours. If both are opened together, the tank will be…CUET (UG) 2026 GAT · 19 May (Shift 1) · QA · Time and Work
Take this paper as a timed test
Real exam timing, instant score, rank and topic-wise analysis.