CUET (UG) 2025 GAT · 19 May (Shift 1) · QA · Question 6
CUET (UG) 2025 GAT · 19 May (Shift 1) previous year question on Time and Work, with the answer and a step-by-step solution.
A and B together can complete a piece of work in 12 days. A alone can complete it in 20 days. B alone will take
- A30 days
- B24 days
- C28 days
- D32 days
Pick an option, then check.
Answer & solution
Answer: Option A
B’s one-day work is the combined rate minus A’s rate: \frac{1}{12}-\frac{1}{20}=\frac{5}{60}-\frac{3}{60}=\frac{2}{60}=\frac{1}{30}. So B alone needs 30 days.
More Time and Work questions
- Q8A can complete a piece of work in 12 days and B can complete the same work in 18 days. Working together, they will…CUET (UG) 2026 GAT · 14 May (Shift 1) · QA · Time and Work
- Q5A is twice as good a workman as B, and together they finish a piece of work in 12 days. A alone would finish it inCUET (UG) 2025 GAT · 3 Jun (Shift 2) · QA · Time and Work
- Q5Twelve men can complete a piece of work in 18 days. How many days will nine men take to complete the same work?CUET (UG) 2026 GAT · 18 May (Shift 1) · QA · Time and Work
- Q5One pipe fills a tank in 6 hours and another empties it in 9 hours. If both are opened together, the tank will be…CUET (UG) 2026 GAT · 19 May (Shift 1) · QA · Time and Work
Take this paper as a timed test
Real exam timing, instant score, rank and topic-wise analysis.