CUET (UG) 2026 GAT · 18 May (Shift 1) · QA · Question 5
CUET (UG) 2026 GAT · 18 May (Shift 1) previous year question on Time and Work, with the answer and a step-by-step solution.
Twelve men can complete a piece of work in 18 days. How many days will nine men take to complete the same work?
- A20
- B22
- C27
- D24
Pick an option, then check.
Answer & solution
Answer: Option D
Men and days are inversely proportional for a fixed quantity of work, so 12\times 18=9\times d, giving d=\frac{216}{9}=24 days. Fewer men must mean more days, which rules out option 1 at a glance.
More Time and Work questions
- Q8A can complete a piece of work in 12 days and B can complete the same work in 18 days. Working together, they will…CUET (UG) 2026 GAT · 14 May (Shift 1) · QA · Time and Work
- Q5A is twice as good a workman as B, and together they finish a piece of work in 12 days. A alone would finish it inCUET (UG) 2025 GAT · 3 Jun (Shift 2) · QA · Time and Work
- Q6A and B together can complete a piece of work in 12 days. A alone can complete it in 20 days. B alone will takeCUET (UG) 2025 GAT · 19 May (Shift 1) · QA · Time and Work
- Q5One pipe fills a tank in 6 hours and another empties it in 9 hours. If both are opened together, the tank will be…CUET (UG) 2026 GAT · 19 May (Shift 1) · QA · Time and Work
Take this paper as a timed test
Real exam timing, instant score, rank and topic-wise analysis.