CUET (UG) 2026 GAT · 18 May (Shift 1) · QA · Question 5

CUET (UG) 2026 GAT · 18 May (Shift 1) previous year question on Time and Work, with the answer and a step-by-step solution.

Time and WorkArithmeticMultiple choiceMedium
Twelve men can complete a piece of work in 18 days. How many days will nine men take to complete the same work?
  1. A
    20
  2. B
    22
  3. C
    27
  4. D
    24
Pick an option, then check.
Answer & solution

Answer: Option D

Men and days are inversely proportional for a fixed quantity of work, so 12\times 18=9\times d, giving d=\frac{216}{9}=24 days. Fewer men must mean more days, which rules out option 1 at a glance.