IPMAT Indore 2026 · Quantitative Ability · Question 18
IPMAT Indore 2026 previous year question on Time and Work, with the answer and a step-by-step solution.
- A7\frac{6}{7}
- B13\frac{2}{3}
- C13\frac{3}{4}
- D13\frac{1}{2}
Answer & solution
Answer: Option B
Step 1 — put the work on a common scale. Take the building as \text{lcm}\left( 12,16 \right)=48 units.
\text{A’s rate}=\frac{48}{12}=4\text{units/day}, \text{B’s rate}=\frac{48}{16}=3\text{units/day}
Step 2 — look at a two-day block. A works day 1, B day 2:
4+3=7\text{units every 2 days}
Step 3 — run as many full blocks as possible.
6\text{blocks}=12\text{days}=42\text{units}
Remaining: 48-42=6 units.
Step 4 — finish off day by day. Day 13 is A’s turn: she adds 4 units, total 46. Remaining 2 units.
Day 14 is B’s turn, at 3 units/day:
\text{time needed}=\frac{2}{3}\text{of a day}
Step 5 — total.
13+\frac{2}{3}=13\frac{2}{3}\text{days}
Answer: Option 2 — 13\frac{2}{3}
Shortcut. Never divide 48 by the two-day average — alternate-day problems must be run in blocks and then finished one day at a time, because the last worker may not need a full day. The fractional part always comes from the final partial day.
More Time and Work questions
- Q3Amisha can complete a particular task in twenty days. After working for four days she fell sick for four days and…IPMAT Indore 2023 · Quantitative Ability · Time and Work
- Q8Arpita and Nikita, working together, can complete an assigned job in 12 days. If Arpita works initially to complete…IPMAT Indore 2025 · Quantitative Ability · Time and Work
Take this paper as a timed test
Real exam timing, instant score, rank and topic-wise analysis.